04 Mar
04Mar

Client - Factory and manufacturing 


Challenges - There are 37 evaporative coolers (or cooling pad) located around the factory to cool the manufacturing areas of this facility. Extreme summer heat (especially for workers on the loading) can be as brutal as you might expect. The cooler pads would scale up rapidly, requiring costly and time-consuming cleaning & replacement of the pads.

Solution - An SB-MAX was installed on seven of the 37 evaporative coolers.

Installed - Ongoing installations of ScaleBlaster have taken place since 2020 to today.


Outcome - Within weeks, management “was impressed with the way the deposits noticeably washed away.” Months later, the project was a total success. There was no more limescale buildup on the cooler pads- resulting in savings in cleaning them and replacing them all thetime. As budgeting allows, the other 30 swamp coolers will have ScaleBlaster installed as well as their massive cooling towers for the rest of the building. 


If you would like any additional information. Please don't hesitate to contact us:  

Mobile: (+66)94 356 9265

E-Mail: info.imcindustry@gmail.com 

Line ID: imcindudtry

Comments
* The email will not be published on the website.